Guides / Choosing a Factory
How to Cut Ten Vietnamese Furniture Factories to Three With a Scoring Sheet
November 21, 2026

A weighted scoring sheet turns a list of ten Vietnamese furniture factories into a shortlist of three without relying on instinct. Give seven criteria a weight, score each factory from 1 to 5 against written definitions, multiply, add and keep the top three. This post is part of our guide to wood furniture manufacturers in Vietnam. It checks several factories against each other, while the factory vetting guide checks one factory in depth.
The checklist below runs in four stages: before the RFQ, the RFQ itself, reviewing replies and quotes and before the first order. Each item says what to do, why and what good looks like.
How the sheet works
The method is known in purchasing as the weighted-point or weighted sum method. The Singapore Institute of Purchasing and Materials Management describes it as weighting the important attributes, scoring each supplier on each attribute, multiplying each score by its weight and totalling the results. The weighted sum model has one known limit: it works only when every score is on the same scale, which is why every row below uses 1 to 5 and no row uses raw figures such as a price or a percentage.
Three habits keep the sheet honest. Write the definition of 1, 3 and 5 for each row before you score anything. Score from evidence, not from the brochure. Where a score rests only on what the factory said about itself, mark it with a flag and re-score it after you hold a sample.
Stage 1: before the RFQ
Build the long list of about ten. Sources are fair exhibitor lists, search, referrals from other buyers and a matching request. Why: ten names gives you room for a failed reply or two. Good looks like a long list where every name makes your product category, not a list of the largest names.
Screen out on category and registration. Remove any plant that makes a different core product. Ask each remaining plant for its registration and tax numbers and compare the registered business activity with what it claims. The National Business Registration Portal has an enterprise search and a Vietnamese and English version of the site. We did not test the search or which fields a free search returns, so also ask for a copy of the registration certificate. Why: this is the cheapest check for factory against trader. Good looks like a registered activity that matches the claim.
Ask the one question. What did you ship the most of last year, by product and by market? Why: it shows the plant’s centre of gravity in one line, as our note on the “we can make anything” sentence explains. Good looks like a product family, a species and a market named without a list of capabilities.
Stage 2: the RFQ
Send the identical package to every name that passed. Why: quotes can be compared only when the assumptions match. Good looks like a package with a drawing or reference photo, the construction per component, species or grade, finish with a reference, hardware and packing, quantity per model and finish, the Incoterm, the date needed and the paperwork your market requires.
Our own RFQ form asks for these fields, so you can use it as a template even when you write to factories directly: name, work email, company, country, target market, a description of the product, product category, quantity, wood species, construction, finish, Incoterm, needed-by date, the paperwork your market needs, a drawing, photo or spec sheet and an NDA tick box. The Incoterm field matters: according to the US International Trade Administration, EXW and FCA suit any mode of transport while FOB and CIF are sea and inland waterway terms, so say which one you want quoted and at which port.
Stage 3: reviewing replies and quotes
Score the replies on the sheet. The weights below are examples. Change them to your priorities and make them sum to 100.
| Criterion | Example weight | Score 1 | Score 3 | Score 5 |
|---|---|---|---|---|
| Product category fit | 25 | Lists many categories, none first | Makes your category among others | Your category is what it shipped most last year |
| MOQ and order size fit | 20 | Your order is far off its normal run | Off, but workable once variants are cut | A planned share of a normal run |
| Capability for your parts | 15 | Answers in adjectives | Names machines or lines, not per part | Part-by-part route, with a test cut |
| Export markets served | 10 | Never shipped to your market | Shipped to similar markets | Shipped to your market and names its packing and paperwork habits |
| Region and port | 10 | Far from its port, thin subcontractor base for your materials | Workable | Deep base for your materials, quotes from the nearest port |
| Sample speed and quality | 10 | Sample fast with no questions | Reasonable time, a few questions | Asks about tolerance, show face, colour and packing before building |
| Reply quality | 10 | Partial, slow | Complete, slow | Complete, asks back, names its subcontractors |
Example weights and definitions are our suggestion, not a published standard. Totals are weight times score divided by 5, giving a score out of 100.
A worked example, with invented scores. Take three imaginary factories. A is a large exporter, B a mid-size plant and C a small workshop. The scores are examples, not data about real plants.
| Criterion (weight) | Factory A | Factory B | Factory C |
|---|---|---|---|
| Product category fit (25) | 5 | 4 | 3 |
| MOQ and order size fit (20) | 1 | 4 | 5 |
| Capability for your parts (15) | 5 | 4 | 2 |
| Export markets served (10) | 5 | 3 | 2 |
| Region and port (10) | 5 | 4 | 3 |
| Sample speed and quality (10) | 3 | 5 | 4 |
| Reply quality (10) | 3 | 5 | 4 |
| Total out of 100 | 76 | 82 | 67 |
Example only: weight times score, summed and divided by 5.
Factory A has the best capability and the best market record, yet it ranks second because your order is far off its normal run. That is the sheet working as intended. If B and A were close, you would send the RFQ to both. Keep price out of the sheet until each plant has quoted the same specification, and normalise construction, finish, packing and Incoterm before you compare numbers.
Read the replies as evidence of how the plant will behave during production. A factory that answers every question, asks sensible ones back and names its subcontractors is thinking about your order. A factory that answers fast with a price and no questions is guessing.
Need a quote for this product? Get matched with a Vietnam wood factory
Stage 4: before the first order
Hold the sample round as the audit. Why: it is the strongest evidence you can collect. Good looks like questions before building, a realistic turnaround and an approved sample that you sign, date and reference in the contract.
Ask for a live video walk through the plant. Why: it catches most of what a visit catches. Good looks like an unedited walk with the date spoken, showing the kiln, the machines and the finishing area that you were told about.
Call two references on a second or third order. Why: most plants perform on a first order, and process shows later. Good looks like a reference who says the second order ran as well as the first.
Re-score after the sample. Why: replace every flagged score with evidence. Good looks like a shortlist that changes order on the evidence and a winner you can explain in a sentence.
Red flags
- A plant that accepts every product category and every quantity without a question.
- A quote with no construction, finish or Incoterm stated.
- A sample that arrives very fast with no questions asked.
- No subcontractor list, or a claim that everything is done in house.
- A registered business activity that does not match the claim.
- Reluctance to show the plant on live video.
- A request for a large deposit before any sample.
What to put in the specification
Send the same package to all three: drawing or reference photo, construction per component, species or grade, finish reference, hardware, packing method, quantity per model and finish, Incoterm and port, date needed and the paperwork your market requires. Say whether you need an NDA. To start, send it through the RFQ page. We reply within 24 business hours and match you with up to 3 Vietnamese wood factories that quote you directly. For the wider view of factory types, regions and capability, return to our guide to wood furniture manufacturers in Vietnam, and read how factory size changes the MOQ row on your sheet.
Sources
- SIPMM: Supplier evaluation and selection, weighted-point method (20 January 2018)
- Wikipedia: Weighted sum model
- National Business Registration Portal, Vietnam (English version)
- US International Trade Administration: Know Your Incoterms
Frequently asked questions
How many furniture factories should be on my shortlist?
Three. Fewer leaves you without a comparison if one declines or quotes badly, and more makes the quotes hard to compare and the follow-up too heavy. Start with a long list of about ten, score it on the same sheet, then send one complete specification to the best three.
What criteria should a furniture supplier scoring sheet include?
Product category fit, MOQ and order size fit, capability for your parts, export markets served, region and port, sample speed and quality, plus reply quality. Weight them to your priorities, score each from 1 to 5 on written definitions and total the weighted scores.
Should price be on the scoring sheet?
Score price only after every factory has quoted the same specification, and normalise construction, finish, packing and Incoterm first. Before that, price differences mostly show different assumptions. Many buyers keep price as a separate column and use the sheet to decide who is allowed to quote.
Can I score a factory I have not visited?
Yes, on evidence you can verify: a live video walk through the plant, the registration record, shipment history by product and market and the quality of written replies. Flag criteria scored on claims alone, and re-score after the sample round, which is the strongest evidence you will get.